Project Recovery First-Look Guide

A structured first look: what the evidence says, who holds authority, what completion actually costs, whether the schedule is real, and which outcomes remain available.

Written for
Owners, lenders and partners holding a stalled or troubled project
Decision it supports
What to establish first when a project has stopped, before choosing a path.
Dates
Published September 18, 2026Updated September 18, 2026

What is inside

  • Four evidence reviews in sequence
  • Authority and obligation mapping
  • Cost-to-complete discipline
  • Schedule reality tests
  • Five honest outcomes, including the ones nobody wants

The full contents

Evidence first

A stalled project is usually not short of opinions. It is short of an organised record.

  • Collect the current contract set, amendments and change orders in one place.
  • Reconcile paid-to-date against installed and accepted work.
  • List open claims, notices, liens and disputes with dates.
  • Gather permits and conditions, including anything expired or lapsed.
  • Identify the last point at which the record was reliable.

Authority and obligations

  • Map who can sign, bind, suspend, terminate and pay today.
  • List obligations with hard dates: loan covenants, approvals, leases, tax and insurance.
  • Confirm insurance and bonding status for the current state of the work.
  • Identify parties whose consent is required for any path forward.
  • Record where authority is contested, rather than assuming it is settled.

Cost to complete

  • Rebuild the remaining scope from the current condition, not from the original budget.
  • Price rework, protection, remobilisation and repricing of expired quotes separately.
  • Treat unresolved claims as a range, not as a number.
  • Hold contingency for discovery; a stalled project reveals more as it reopens.
  • State clearly what has not been investigated and what that could change.

Schedule reality

  • Test whether approvals, utilities and inspections are still valid or need renewal.
  • Confirm long-lead availability at today's dates, not the original ones.
  • Sequence restart activities that must happen before any production work.
  • Identify the seasonal and jurisdictional constraints that cannot be compressed.
  • Separate a schedule from a hope: each duration needs a basis.

Outcomes that remain available

  • Restart and complete under corrected controls.
  • Restart with a different delivery structure or delivery party.
  • Pause deliberately, protect the asset and preserve optionality.
  • Sell or transfer in the current condition to a party equipped to finish.
  • Wind down in an orderly way. Choosing this early usually costs less than choosing it late.

This is the document's actual contents — the PDF is the same material set out as a working sheet, with room to write against each item.

Where it applies

Project Recovery

How a first-look review is scoped and what outcomes are honestly available.

Advisory & Consulting

Second-opinion and owner-side review work.

The writing behind it

First-look review of a stalled project stays public in full. This document is the same guidance as a sheet you can work through.

Have it emailed instead

Send me a copy of this document.

Entirely optional — the download above is the same file, and needs nothing from you.

We record your name, email address, which document you asked for, its version, the choice you made about The Project Brief and the privacy notice version shown here (2026-09-18.1). Nothing else is collected on this form, and the record is not sent to any third party. To ask what we hold, correct it or have it deleted, reply to the delivery email.

General working material, not advice for a specific project. Nothing in this document is an offer of financing or securities, a commitment of funds, an appraisal, or a legal, tax or engineering opinion. Verify every item against your own counsel, licensed design professionals and the authority having jurisdiction.

Explore Project Recovery

The first task is an organised record, not a rescue plan.