Skip to content

Checklist · 4 pages · version 2026-09-18.1

Owner's Project Control Checklist

The controls an owner needs in place — authority, documents, money, schedule, information — before construction makes decisions irreversible.

Written for
Owners and owner representatives carrying delivery risk
Decision it supports
Whether you actually control your project, or only receive reports about it.
Dates
Published September 18, 2026Updated September 18, 2026

What is inside

  • Five control domains with specific tests
  • Authority thresholds and who holds them
  • Document control that survives staff turnover
  • Payment and change controls
  • A monthly owner review agenda

The full contents

Authority

  • One written authority matrix: who approves what, to what value, with what evidence.
  • Named alternates for every approver, so absence does not stall or bypass control.
  • A rule that verbal direction on site is not an approval and does not bind the owner.
  • Separation between the person requesting a change and the person approving it.
  • A record of every approval in one place, not across individual mailboxes.

Documents

  • A single current set marked as current, with superseded sets clearly retired.
  • Version control on drawings, specifications and the assumptions register.
  • A log of requests for information and their answers, with dates.
  • Consultant scopes in writing, including what each consultant is not doing.
  • Permits and conditions tracked against the work they govern.

Money

  • A cost report tied to committed values, not to early estimates.
  • Pay applications checked against installed work, lien waivers and retainage terms.
  • Change orders priced, approved and reflected in the current cost report before work proceeds.
  • Contingency drawdown tracked with the reason for each release.
  • Allowances and unresolved scopes listed openly as exposure, not as settled cost.

Schedule and information

  • A baseline schedule and a current schedule kept as separate records.
  • Float ownership stated, so it is not consumed silently.
  • Long-lead items tracked from order date, not from installation date.
  • One reporting format the owner actually reads, on a fixed cadence.
  • An escalation rule: what must reach the owner within 24 hours regardless of cadence.

Monthly owner review agenda

  • Decisions taken since the last review, and by whom.
  • Open decisions the owner must make, with deadlines and consequences.
  • Cost position: committed, changed, remaining, exposed.
  • Schedule position: baseline, current, causes of movement.
  • Risks that became real, and the assumptions that failed.

This is the document's actual contents — the PDF is the same material set out as a working sheet, with room to write against each item.

Where it applies

Advisory & Consulting

Owner-side advisory, review and representation work.

Construction

Owner-side oversight, distinct from regulated contracting or inspection.

Have it emailed instead

Send me a copy of this document.

Entirely optional — the download above is the same file, and needs nothing from you.

We record your name, email address, which document you asked for, its version, the choice you made about The Project Brief and the privacy notice version shown here (2026-09-18.1). Nothing else is collected on this form, and the record is not sent to any third party. To ask what we hold, correct it or have it deleted, reply to the delivery email.

General working material, not advice for a specific project. Nothing in this document is an offer of financing or securities, a commitment of funds, an appraisal, or a legal, tax or engineering opinion. Verify every item against your own counsel, licensed design professionals and the authority having jurisdiction.

Explore Advisory & Consulting

Control is cheapest to install before the irreversible decisions.